The update yesterday told me we're looking at the following timeline for various bits and pieces:
- Fixing of Hebel at front of house and first layer of render: Monday
- Replacing glass in front door: Next week.
- Front render complete: Friday
- Internal painting fix-ups: Next week
- Gutters and downpipes installed and checked: Following week
- Driveway: Following week
- Internal QA start: Three weeks
- PCI scheduling: About four weeks.
Of course the actual PCI date could be months away :(